Driveway construction (Design-build), Ithaca, NY:
Pressure-treated continuous curved curb.

Construction process: <-- previous | 1 | 2 | 3 | 4 | 5 | next -->
 
ochshorn driveway curb
After the driveway fabric and drainage pipes are in place, we begin installing a pressure-treated wooden curb to separate the gravel from the lawn. The first layer consists of 6x6 members rated for ground contact; where the line curves, some of the 8-foot long pieces are cut in half.
  ochshorn driveway curb
The second and third layers consist of pressure-treated 2x6 boards, staggered so that none of the joints are aligned. These boards are not rated for ground contact, but their position above the 6x6 base should protect them from continual contact with water. They are screwed in place with 3" deck screws.

ochshorn driveway curb   ochshorn driveway curb
I install the curb as it curves around the corner of the addition (left) and at the end of the driveway, near the garage.
ochshorn driveway curb
The finished curb is one continuous "snake," over 100 feet long from the garage to the street.
  ochshorn driveway curb detail
At the street end, the curb extends above the top surface of the driveway, to protect the shallow sewer pipe that we discovered is barely six inches below grade immediately to its right.

ochshorn driveway curb detail
Detail of the pressure-treated curb, showing how the top layers of 2x6 boards follow the curve. The 6x6 below will be covered by gravel on one side, and soil on the other; therefore, it need not be precisely fitted together.

ochshorn driveway curb and landing at side entrance
At the side entrance to the addition, the curb extends into a pressure treated landing.
  ochshorn driveway curb: planting grass
Susan sprinkles grass seed as we repair the lawn next to the curb.

Construction process: <-- previous | 1 | 2 | 3 | 4 | 5 | next -->

Related links:
addition
Design-build addition to house
  renovation
Design-build renovation of original house
  rain harvesting
Rainwater harvesting

first posted: 19 July 2007 | last updated: 22 July 2007

Copyright 2007 J. Ochshorn. All rights reserved. Republishing material on this web site, whether in print or on another web site, in whole or in part, is not permitted without advance permission of the author.