image ochshornDesign.com
Architectural practice
Jonathan Ochshorn
Jonathan Ochshorn Architect: phone 607 277-7791 (607 255-1194 Cornell office)
207 Water Street, Ithaca, NY 14850

contact | rock'n'roll homepage | academic homepage | ochshornDesign homepage
.

Design-build addition to residence, Ithaca, NY

previous week | next week | "addition" homepage

Weeks 46-52: April 18, 2005 - June 5, 2005


constructionWe finally remove the scaffolding from the front elevation, and begin installing the final row of Hardipanel siding.

constructionconstruction
Meanwhile, on the south side, Accufab begins installing the stainless steel stair truss they fabricated. I designed a bracket to be installed first, both to facilitate the erection process and to allow for tolerances (for construction inaccuracies). The bracket is fastened to the addition with 6" stainless steel lag screws (left); the stair truss then is inserted into the bracket (right).

constructionconstruction
The lower end of the truss is then aligned (left) and fastened to the addition with more lag screws (right).

constructionconstructionconstruction
The hardest part of the stair installation wasn't the fastening; it was getting it up into place. The sequence is shown in these images: on the ground (left); being lifted up (middle); and being slid along the scaffolding into position (right).

constructionconstructionconstruction
Once the stair truss is in place, I can fabricate a relatively conventional stair using pressure-treated lumber. I cut the stringers (left); and fasten one to the truss and the other to the addition wall.

constructionconstructionconstruction
The stringers are supported by the truss on stainless steel clip angles, shown before (left); and after (middle). On the addition side, the stringers are fastened through 2x2 pressure-treated spacers using 6" lag screws recycled from the demolished scaffolding brackets (right). The only trick here was finding the studs behind the Hardipanel siding.

constructionOnce the stringers are fastened, the scaffolding is removed, and landings and treads are screwed into place, starting at the bottom.

constructionconstruction
When I reach the top, it is possible to stand on the roof and look back at the stair. The actual roof deck, to be placed over the existing EPDM membrane, will come later this summer.

constructionWith the scaffolding removed below the stair, it is now possible to install the next row of Hardipanel siding, revealing three more windows into the studio and bathroom. The early morning light from the south-east casts shadows on the southern wall.

constructionWe complete the soffit under the cantilevered stair, using inexpensive 1/2" sanded plywood coated with spar varnish. A motion-sensitive light is rescued from the attic and put into position in front of the side entrance.

constructionconstruction
Before removing the scaffolding planks, we install an air conditioner for the studio space. We purchased the less-expensive window a/c units (rather than the more-expensive "thru-the-wall" units), so the opening in the wall mimics the operation of a double-hung window (left). With the final scaffolding removed, we complete the exterior siding (right), put on the final 2 coats of exterior paint, and move inside for the final tasks.

constructionconstruction
This is how the addition looks from the outside: the east elevation (left); and the south elevation (right).

constructionconstruction
Two images of the north elevation: with the red maple (left), and more recently with some flowers in the foreground (right).

constructionWith the scaffolding removed, I re-build the two interior stairs using the 2x12 scaffolding planks for the treads, and ripping (cutting parallel to the grain) the old temporary 2x10 treads for the new risers. To comply with the NYS building code, I begin installing gypsum board in the closet under stair #1.

previous week | next week | "addition" homepage

last updated: 06 June 2005