Weeks 24-25: November 15 - November 28, 2004


constructionWe install the remainder of the windows in anticipation of the drywall work.

construction. construction
The small side window above the entrance is shown installed (left) and with adjacent Hardipanel siding (right).

constructionIt's too cold to work outside much so we complete the plywood finished ceiling and walls in stair #2.

construction. construction
The "Rock Company" delivers 12-foot long sheets of gypsum board through the second-story window opening.

construction. construction
To minimize joints that would require taping and spackling, the drywall is hung in one piece over the windows, and cut out afterwards (left); ceilings are hung in the double-height studio space using scaffolding (right).

constructionThe studio space approaches its final form; this view is from the mezzanine overlooking the east- and north-facing windows.